Preamble
The work generally required was to carry out the installation of antennas, cables, and brackets required for the radio installation and to carry out office cabling for the Local Area Network and radio remotes.
Work Included:
- Mount four antennas: Antennas 1, 2, 3, and 4
- Run coaxial feeders FDR2, through to 8 inclusive
- Design and fabrication of a cable bridge between the crane column and the Communications Office Container and fitting cable entry through container wall
- Fabricate and install Inmarsat Antenna mounting bracket either alternative shown in drawing 13868-2 pages 2 and 3
- Fabricate and install Fixed Link Antenna mounting bracket shown in drawing 13868-2 page 4
- Run Category 5 screened Ethernet cable D1 through D5 inclusive
- Install cable trunking around inside of control room container